Skip to content

Software Development

The Software Development Life Cycle Explained with an Example Project

The seven SDLC phases explained through one illustrative project, with the deliverables, people and security activities in each phase, and how Waterfall, Agile and other models organize them.

VisionColab TeamSoftware engineering & AI 6 min read
Software development life cycle – the SDLC phases arranged in a loop

In shortThe software development life cycle (SDLC) is the sequence of phases every software product goes through: planning, requirements, design, development, testing, deployment, and maintenance. Models such as Waterfall and Agile do not change these phases; they change how often you repeat them. In modern projects, security and testing run through every phase rather than waiting until the end.

Most SDLC guides list the phases and a dozen models, then stop. That leaves the important questions unanswered: what is actually produced in each phase, who is involved, and what it looks like on a real project. This guide answers those through one example project, followed from first idea to running product.

The example project

To keep things concrete, we will follow an illustrative project: a group of physiotherapy clinics wants an online booking system. Patients should book, move and cancel appointments on the web and on their phones. Reception staff need a schedule view, and the system must connect to the clinics’ existing payment provider and send reminders. This is a composite example for teaching, not a specific client.

The seven phases at a glance

PhaseKey questionMain deliverablesWho leads
1. PlanningShould we build this, and why?Goals, success measures, budget range, risksProduct owner, sponsor
2. RequirementsWhat exactly must it do?User stories, acceptance criteria, non-functional requirementsProduct owner, business analyst
3. DesignHow will it work and look?Prototype, architecture, data model, API contractsDesigners, tech lead
4. DevelopmentBuild itWorking code, code reviews, automated testsDevelopers
5. TestingDoes it work, safely, for real users?Test results, fixed defects, security checksQA, developers
6. DeploymentRelease itLive system, release notes, rollback planDevOps, tech lead
7. MaintenanceKeep it healthy and improvingMonitoring, updates, new featuresWhole team

Phase 1: Planning

Planning decides whether the project is worth doing. For the clinics, the problem is that reception staff spend much of the day on the phone and missed appointments cost money. Success measures might be the share of bookings made online and the no-show rate. The team also lists major risks: patient data privacy, integrating with the payment provider, and staff adoption.

Output: a one-page brief with goals, measures, rough budget and timeline, and the decision to proceed with a discovery phase.

Phase 2: Requirements

The team interviews reception staff, therapists and a few patients. Requirements are written as user stories with clear acceptance criteria, for example: “As a patient, I can move my appointment up to 24 hours before it starts, and I receive a confirmation.”

Non-functional requirements matter just as much: data protection rules for health information, accessibility, supported devices and expected load. These are the requirements most often forgotten, and the most expensive to add later.

Output: a prioritized backlog, with the first release limited to booking, rescheduling, canceling, reminders and the staff schedule. Online payments and reporting move to release two. Our guide to scoping an MVP explains how to make these cuts.

Phase 3: Design

Design covers two things. Product design produces user flows and a clickable prototype, which five patients test before any code is written, using a method like the one in usability testing on a budget. In our example, testing shows patients cannot find the reschedule option, so it moves to the confirmation email and the home screen.

Technical design decides the architecture: a web app and a cross-platform mobile app sharing one backend API, a relational database, and a job queue for reminders. The team writes the API contract first, following API design best practices, and runs a short threat model to identify how patient data could leak.

Output: tested prototype, architecture diagram, data model, API specification and a list of security controls.

Phase 4: Development

Developers build in two-week sprints. Each sprint ends with a working increment the clinic can try on a staging environment. Every change goes through code review and automated tests, and a continuous integration pipeline runs those tests and a dependency vulnerability scan on every commit. If the team is remote, the practices in running agile sprints with a remote team apply.

Output: working, reviewed, tested code delivered in increments.

Phase 5: Testing

Testing happens continuously, but some checks need the whole system together:

  • Functional tests against each acceptance criterion.
  • Integration tests with the payment provider’s sandbox and the email and SMS services.
  • Performance tests for Monday mornings, when bookings peak.
  • Security testing, including access control checks so one patient can never see another’s appointments.
  • User acceptance testing by reception staff on realistic days.

Phase 6: Deployment

The team releases to one clinic first, watches for problems for a week, then rolls out to the others. Deployment is automated so it can be repeated reliably, and there is a written rollback plan. Staff get a short training session and a one-page guide. The mobile apps go through store review, so the team submits them a few days before launch.

Phase 7: Maintenance and improvement

Maintenance is the longest phase, and the one most budgets underestimate. It includes:

  • Monitoring uptime, errors and reminder delivery, with alerts to an on-call person.
  • Security patches and updates to libraries, frameworks and mobile OS versions.
  • Fixing bugs reported by staff and patients.
  • Measuring the success metrics from Phase 1 and planning release two from real usage data.

And so the cycle starts again: release two (online payments and reporting) goes back through planning, requirements, design and the rest.

Security runs through every phase

Treating security as a final test is the most expensive way to do it. NIST’s Secure Software Development Framework (SP 800-218) groups secure practices into preparing the organization, protecting the software, producing well-secured software and responding to vulnerabilities. In practice that means:

PhaseSecurity activity
RequirementsIdentify regulated data and privacy obligations
DesignThreat modeling, choosing secure defaults
DevelopmentCode review, dependency scanning, secrets kept out of code
TestingAccess control tests, vulnerability scans, penetration test where justified
DeploymentHardened configuration, least-privilege access
MaintenancePatching, monitoring, a process for handling reported vulnerabilities

SDLC models: how the phases are organized

ModelHow it worksBest forMain risk
WaterfallEach phase completes once, in orderFixed, well-understood, regulated scopeProblems discovered late
V-modelWaterfall with a matching test stage for each design stageSafety-critical and highly regulated systemsRigid when requirements change
Iterative / incrementalBuild the product in slices, each passing through all phasesLarge products delivered in releasesNeeds a stable architecture early
SpiralRepeated cycles driven by risk analysisLarge, high-risk projectsHeavy process for small teams
Agile (Scrum, Kanban)Short cycles delivering working software, with frequent feedbackProducts where needs evolveScope drift without a strong product owner
DevOpsAgile plus automated build, test, release and monitoringProducts released frequentlyRequires investment in automation

Our example project used Agile sprints for development, with a short upfront planning and design phase, which is how many teams work in practice. The Scrum Guide describes the most widely used Agile framework.

Frequently asked questions

Which SDLC phase is the most important?

Requirements, because mistakes there are carried into every later phase. Clear acceptance criteria prevent more problems than any amount of testing at the end.

Does Agile skip the SDLC phases?

No. Agile runs all the phases in small loops, every sprint, instead of once for the whole project.

What is the difference between SDLC and DevOps?

The SDLC describes the phases. DevOps is a way of working that automates and connects the later phases (build, test, release and monitoring) so they can run many times a day.

How long does each phase take?

It depends on scope. In an Agile project, planning and design may take a few weeks upfront, development runs in sprints, and maintenance continues for the life of the product.

Plan your project with us

VisionColab runs projects from discovery to maintenance for web, mobile and AI products. See our web development services or book a free consultation.

Written by the VisionColab team

VisionColab designs and builds AI, web, mobile and cloud software for businesses. Our guides explain the decisions, costs and trade-offs involved in planning a software project.

Have a project in mind?

Share your goals and constraints. We will suggest a realistic scope and the right technology approach.